If you are influencing factors that create changes to the cost of the project, which process are you using?

A. Negotiate Costs
B. Estimate Costs
C. Control Costs
D. Determine Budget

Answer: C



If you are requesting a vendor quote for a defined scope, what is the recommended contract type?

A. Fixed price
B. Commission
C. Cost reimbursable
D. Time and materials

Answer: A