PMI PMP Question Answer

Perform Integrated Change Control includes several configuration management activities. Which of the following is not part of Perform Integrated Change Control?

A. Change request
B. Configuration Verification
C. Configuration Status Accounting
D. Configuration Identification

Answer: A


After brainstorming potential project risks, what is the recommended method for prioritizing these risks and their mitigation plans?


A. RACI chart
B. Control chart
C. Fishbone Diagram
D. Probability and impact matrix

Answer: D