Linda has been assigned to establish a PMO in her organization. Linda believes that this project cannot be successful unless all of the key project stakeholders support the project. She also believes that she needs to pay special attention on stakeholder management to ensure success of this project. As the first step, she needs to develop her stakeholder register. Which of the following processes must be started by Linda to produce the project stakeholder register?
A. Plan Stakeholder Management
B. Control Stakeholder Engagement
C. Identify Stakeholders
D. Manage Stakeholder Engagement
Answer: C
The Create WBS process identifies the deliverables at the __________ level in the Work Breakdown Structure (WBS).
A. Lowest
B. Any
C. Tenth
D. Highest
Answer: A
No comments:
Post a Comment
Note: only a member of this blog may post a comment.