A fundamentally functional organization creates a special project team to handle a critical project. This team has many of the characteristics of a project team in a project organization and has a Project manager dedicated to the project. Such an organization would be called:

A. A projectized organization
B. A functional organization.
C. A strong matrix organization
D. A composite organization

Answer: D


As you are creating the Activity List, which technique is recommended for subdividing the project into smaller components called activities?

A. Decomposition
B. Rolling Wave Planning
C. Expert judgment
D. Deconstruction

Answer: A