A project manager has finished the project. He knows that the project scope has been completed and is within cost and time objectives set by management. Management, however, says that the project is a failure, because the original schedule was for 27 weeks and the project was completed in 33 weeks. If the project baseline was 33 weeks, the project is a success because: 

A. It only had six weeks of changes.
B. It was completed within the baseline.
C. There were so few changes.
D. There was good communication control.

Answer: B