The Java development of a project is outsourced to Indi a. The project schedule is starting to slip. What is the LEAST likely cause of the slippage?

A. Lack of competent programmers
B. Cultural influences
C. Internationalization
D. Communication

Answer: A                                                   

A project manager has made a change to the project. What should she do NEXT?

A. Assign resources.
B. Revise the project management plan and/or project documents.
C. Evaluate impact.
D. Request change control board involvement.

Answer: B