Wednesday, 3 December 2014

PMP Question Answer

Question:1

In your project, you create project documents which will help you when managing the project.
Which of the following is NOT an example of project documents?

A. Schedule baseline
B. Assumption log
C. Roles and responsibilities
D. Risk register

Answer: A


Question: 2

You have asked your programmer to give you an estimate of how long she will take to complete a
software program. She mentions that she would most probably get the job finished in 2 hours. But if
she runs into some issues with doing unit -testing for the program, it could take her as long as 7
hours. On t he other hand, she may be able to pick up a similar program from the organization
process assets, in which case it will take her only 1 hour. What is the standard deviation?

A. 2 hours
B. 1 hour
C. 3 hours
D. Cannot be determined from the provided information

Answer: B

No comments:

Post a Comment